Run Coordination
Welcome to RUN 2012
| People | Shift | ALICE | |||
|
|
|
|||
| LHC | |||||
|
|
|||||
Timetable 2010
| • January 4th-24th | Work on DCS/DAQ/Trigger issues with individual detectors. No ALICE shifts | |
| • January 25th- 31th | Start of common sessions for DAQ and DCS work with groups of detectors. Normal working hours | |
| • January 31th February 14th |
Start of 16/7 shifts. Day and evening shifts for DCS and ERP sessions. Night shift for ‘unattended’ running. Cosmics requirement: ITS pT dependent alignment |
|
| • February 15th-19th | Global ALICE running 24/7. Beam on TED and cosmics. |
For updated news please visit the System Run Coordinator's meetings in Indico and the LHC program Coordinator's page.
Timetable 2009
| • July 10th - 13th 2009 | T12 to TED extraction test | |
| • September 25th - 26th 2009 | TI2-TI8 to TED extraction test | |
| • October 21st | short TED splash event test | |
| • October 23th-26th 2009 | TI2 injection test, beam (first HI) through ALICE | |
| • November 7th - 8th | Second injection test - HWC permitting | |
| • Cosmics Aug-Nov 2009 | statistics archive week 33-43 | |
| • November 20th-on | First circulating beam running partition | |
| • December 2009 | Plan for THE weekend 12.5-6 √s = 0.9 LHC plan for THE weekend and 2.4 TeV p+p | |
| • December 17th - January 7th | Xmass break |